In the newsletter for this month, we will be discussing the progress of on-going projects by Bin Faqeeh. We also wish you and your family a safe and blessed Holy Month.
 
img
img
img
 
Somewhere Residences
 
The construction works is in continuum with Bin Faqeeh’s newest development. At the current stage, the structure works are completed on the 6th floor and the 7th floor structure works are in progress along with the swimming pool. On the other hand, the block work is ongoing at the site. For more details about Somewhere Residences, please visit our website or contact us on 38000002 or 00966533883311 (KSA).

 

 
img
Waterbay Residence by Roberto Cavalli
 

Waterbay Residence by Roberto Cavalli progress is also at full speed. The ceiling works is 70% done and the fixing of glass and aluminum is almost completed. Wall painting, tiles and marble fixing, and fixing of staircases’ handrail works are ongoing. The lift installation works are also completed. Click here to view the project's latest progress report or visit our website to learn more about the project.

 
img
Paramount Residence BH, Waterbay

Paramount Residences Bahrain, Waterbay development progress is at full speed. MEP work in basements, ground floors, and typical floors are on-going, along with the plastering of walls in typical floors, staircase screed preparation, and glass and aluminum works. Lift installation works are already completed. Click here to give you a full insight of the project's latest progress report, and visit our website to know more about the project.

 
 
img
Watebay Middle

Waterbay Middle tower has now an electricity power connection supplied by the Electricity and Water Authority. Therefore, Bin Faqeeh will start handing over the units to its owners on floor by floor basis starting with the first and second floors.

Owners will be contacted by their Property Advisor to schedule a meeting to commence the snagging and inspection of their units. Due to the current situation, Bin Faqeeh launched a new and exclusive service to be the first in the Kingdom of Bahrain where units will be handed over digitally through WhatsApp video call to ensure the health and safety of their clients.

 
 
img
Layan

Layan construction is progressing smoothly. Structure works are fully over from ground floor, first floor and mezzanine floor in zones 1, 2, and 3. From zone 4, 5, and 6, the structure works from the ground floor to third floor are also fully completed. The project's latest progress report can be viewed here, and visit our website for more information about Layan.

 

 
 
 
BF BLOGS
Be posted instantly by checking out the monthly newsletters!
The updates of this month are about the following:
PropTech's Role During the COVID-19
Tips by Bin Faqeeh How to Virtually Connect with Consumers During the Crisis
Coronavirus Pandemic and the Digital Economy
Brand Management with the Behavioral Changes Caused by COVID-19
“Be Aware Bahrain” App
Best Practices When Working from Home
 
section image
 
Alsidra Villas Project – Phase 1
 

Alsidra project is at an advanced construction stage. The main contractor is working at full speed with the aim of completing the villas, and have it delivered to the owners on time. The plastering and painting works are taking place, making the Phase 1 villas at the final stage of construction. In terms of the internal works, the internal plastering and ceiling, toilets tiles are going on. Also, the designated subcontractor began fixing the aluminum and joineries. Click here to see the latest progress report of ALSIDRA development.

 
 